Project Portfolio

Industry:  Energy

Services: Planning and Scheduling, Estimating and Cost Engineering

Duration: 8 months

Estimated Cost: Up to $5,000,000

 

Power Services Project

CHALLENGE: Align the schedule and construction cost estimating services for Power Services’ projects.

SOLUTION:  ACM provided estimating support services for scheduled refueling outages at two nuclear power generation stations. ACM:

  • Gathered all of the information available for each project;
  • Communicated with project managers, field staff, and owner representatives to establish the Work Breakdown Structure (WBS) work flow and sequencing;
  • Addressed staffing plans and equipment needs;
  • Aligned craft availability and jurisdictions.
(1337)